Intelligent solutions for effective energy management.

Investor: Project-building center “Domit” Lebane

Contractors: PB Center “Domit” Lebane and R&D Center “Alfatec” Niš

The power plant is located at the very entrance in Leskovac. It is designed for a total power of 210 kW, and in the first phase a power plant with a total power of 30 kW is realized. At this stage, panels are mounted on a roof structure. Monocrystalline panels of 260W, dimensions 157×108 cm were used. Inverters are of Schneider Electric, model CONEXT TL 15000 E.

The power plant was put into operation on 27.08.2012.

 